  1. Question 1A city council wants to replace its paper permit process with an online service. Nobody is sure how applicants will actually use it, and early prototypes keep revealing new requirements. Why is this a good fit for Scrum?

    1. The work is complex: what is needed only becomes clear by building, delivering and observing
    2. Scrum provides a detailed method for gathering every requirement before development begins
    3. Scrum guarantees the service is delivered by a fixed date because Sprints have fixed lengths
    4. The council can skip stakeholder involvement because the Scrum Team decides everything internally
    Show answer

    Answer: A. Scrum exists to help people generate value through adaptive solutions for complex problems, where knowledge comes from experience rather than from a plan made in advance.

    Exam trap: Scrum is chosen for complex work because it learns its way to the answer, not because it predicts dates or scope more precisely.

  2. Question 2A new Scrum Master is asked by a director to provide 'the official Scrum estimation technique' so all teams estimate the same way. What is the most accurate response?

    1. Story points with the Fibonacci sequence, since that is the estimation scale the Scrum Guide specifies
    2. Scrum defines no estimation technique; each team chooses practices that work within the framework
    3. Hours per task, because the Guide requires items to be broken into work of one day or less
    4. The Product Owner estimates each item so that the Developers can focus on delivery
    Show answer

    Answer: B. Scrum is purposefully incomplete. It defines what is needed to implement empirical theory and leaves practices like estimation to the people using it.

    Exam trap: If a practice is not in the Scrum Guide, Scrum does not require it, however universal it seems in your organisation.

  3. Question 3Eight months into a twelve-month plan, a programme has produced detailed documents but nothing anyone can use. A second team working in Sprints has released something usable every two weeks. Which team is better placed to forecast what it will deliver next quarter, and why?

    1. The planned programme, because a detailed long-range plan contains more information
    2. Neither, because forecasting is not compatible with an empirical approach
    3. The Sprint team, because its forecasts rest on evidence from delivered Increments
    4. The planned programme, because its scope has been fixed since the start
    Show answer

    Answer: C. An iterative, incremental approach optimises predictability because each delivered Increment produces real evidence about progress and value.

    Exam trap: Scrum improves predictability through frequent evidence, not through longer or more detailed plans.

  4. Question 4The Sprint Backlog shows almost every task as in progress because Developers move cards as soon as they think about a task. Stakeholders read it as a sign the Sprint is going well. What is the main risk?

    1. The board is too detailed, which slows down the Daily Scrum
    2. Decisions are being made on a picture that hides how little is finished
    3. Stakeholders are not allowed to see the Sprint Backlog during the Sprint
    4. The Scrum Master is not updating the board on the Developers' behalf
    Show answer

    Answer: B. Low transparency leads to decisions that diminish value and increase risk. The board is visible but misleading, so everyone inspecting it reaches the wrong conclusion.

    Exam trap: Visible is not the same as transparent: an artifact everyone can see can still mislead everyone who reads it.

  5. Question 5A team has finished between six and nine items per Sprint over its last eight Sprints. About forty items remain before a planned release. Which forecast best reflects empiricism?

    1. Exactly five Sprints, based on the best Sprint so far
    2. Roughly five to seven Sprints, revisited each Sprint
    3. No forecast, since complex work cannot be forecast
    4. Whatever date the sponsor has already announced
    Show answer

    Answer: B. Forty items at six to nine per Sprint gives roughly five to seven Sprints. A range from observed throughput, updated each Sprint, is grounded in what has already happened.

    Exam trap: Forecast from your own history, as a range, and revise it; never from a target or your best day.

  6. Question 6In the Kanban Guide for Scrum Teams, what does work item age measure?

    1. Time from start to finish of completed items
    2. Items finished per unit of time
    3. Time since an unfinished item was started
    4. Time an item spent in the Product Backlog
    Show answer

    Answer: C. Work item age is the time between when a work item started and now, and it applies only to items still in progress.

    Exam trap: Cycle time looks back at finished items; work item age watches unfinished ones.

  7. Question 7A team of six Developers routinely has fifteen items in progress. Cycle times are long and unpredictable. What does the Kanban Guide for Scrum Teams suggest considering first?

    1. Lowering the amount of work in progress
    2. Starting more items so that idle time is avoided
    3. Adding Developers to raise throughput
    4. Lengthening the Sprint to fit the longer cycle times
    Show answer

    Answer: A. Little's Law shows that, for a given throughput, more work in progress means longer cycle times. The guide says lowering WIP is the first thing to consider.

    Exam trap: Long cycle times: first reduce WIP. Starting more never finishes more.

  8. Question 8A team using Kanban starts a new item only when its work in progress drops below its agreed limit. What is this called?

    1. A push system
    2. A pull system
    3. A Sprint Backlog
    4. A release train
    Show answer

    Answer: B. Limiting WIP creates a pull system: the team pulls new work only when it has capacity, signalled by WIP falling below the limit.

    Exam trap: WIP limits turn push into pull.